Road Work – July 2019

Prospect Road & Trail Road South – Paving Overlay Project:

Work is scheduled to begin Friday, July 12th with laying the scratch coat;  Monday, July 15th the overlay process will begin.  The entire project will take several days to complete.  During this time the road will be closed to thru traffic, but remain accessible to residents, emergency vehicles, mail delivery, and garbage pickup.  There may be delays where construction equipment may block the travel lane momentarily.  Driveways may be inaccessible for short periods of time during working hours but will be fully accessible after work hours.

2019 Seal Coating Project:

The following roads will be sealcoated:

Aberdeen Road (from Mill Road to Old Hershey Road)

Beverly Road (from Old Hershey Road to Hershey Road)

Mill Road (from Hillside Drive to Township Line)

Old Hershey Road (from Rockwood Drive to Township Line)

Work for the sealcoating is scheduled to begin the week of July 15th.